Timeline for Milestones |
January |
18 - Allocated
project
|
24 - Established
project team and preliminary system specifications
|
31 - Familiarized
with software tools and refinement of system specifications
|
February |
07 - Analyzed and
modeled requirements
|
14 - Developed
software design
|
28 - Implemented
software
|
March |
14 - Computerized
Match-making System Completed |
|
|
This Week
- Familiarization with development platform and software
tools
- Install necessary software packages
Next Week
- Analyze, model and refine preliminary requirements
- Print and keep a hardcopy of the refined preliminary
requirements
|